Each year the Town of Markham repairs our roads according to a schedule in order to keep our roads in a good condition in a cost effective way. By regular maintenance, small repairs can be done before they become a major and costly problem.
On this page, I post a weekly report for you, so you will know which streets to avoid during the construction period.
| Work Plan for the period July 26 to July 30, 2010 | ||||
| Street | From | To | Ward | Type of Work |
| Wooten Way South | Hwy. No. 7 | Delmark Boulevard | 5 | Asphalt Rehabilitation |
| Bakerdale Dr | Entirety | 4 | Asphalt Rehabilitation | |
| Jolyn Crt | Entirety | 4 | Asphalt Rehabilitation | |
| Walkerton Drive | Southdale Drive | Southdale Drive | 4 | Concrete Rehabilitation |
| Lake Vista | Entirety | 4 | Concrete Rehabilitation | |
| Raymerville Drive | Woolen Mill Road | McCowan Road | 5 | Asphalt Rehabilitation |
| Larkin Ave | Entirety | 5 | Asphalt Rehabilitation | |
| Tavistock Crt | Entirety | 4 | Asphalt Rehabilitation | |
| Coulson Crt | Entirety | 4 | Concrete Rehabilitation | |
| Lake Vista | Entirety | 4 | Concrete Rehabilitation | |
| Valleycrest | Entirety | 4 | Concrete Rehabilitation | |
| Anticipated Work Plan for the following week | ||||
| Street | From | To | Ward | |
| Avoca Drive | Swansea Road | Kennedy Road | 3 | Concrete Rehabilitation |
| Eton Street | Swansea Road | Kennedy Road | 3 | Concrete Rehabilitation |
| Note: | ||||
| 1.Weather and crew accomplishment may delay completition of the proposed work within the specified time frame | ||||
| 2.Advance notice will be delivered to residents/occupants several days prior to commencement of construction. | ||||
| 3.Street are subject to removal pending budget constraints | ||||
| Rehabilitation Work Completed to Top Asphalt | ||||
| Street | From | To | Ward | Type of Work |
| Pipher Gate | Larkin Ave | Tilman Cir | 5 | Asphalt Rehabilitation |
| Tilman Cir | Larkin Ave | Tilman Cir | 5 | Asphalt Rehabilitation |
| Follett Crt | Larkin Ave | North Limit | 5 | Asphalt Rehabilitation |
| Daniel Crt | Entirety | 5 | Asphalt Rehabilitation | |
| Enos Gate | Entirety | 5 | Asphalt Rehabilitation | |
| McCarty Court | Heisey Dr | Fincham Avenue | 5 | Asphalt Rehabilitation |
| Heisey | Larkin Ave | McCarty Crt | 5 | Asphalt Rehabilitation |
This web site provides a forum where I can bring you up to date on issues and events at the Town of Markham that affect the quality of living in our Ward.
To contact me regarding any issue please click here for the contact page.
Please visit this page to see what some residents of East Markham have to say about John.