2010 Road Rehabilitation Program

Each year the Town of Markham repairs our roads according to a schedule in order to keep our roads in a good condition in a cost effective way.  By regular maintenance, small repairs can be done before they become a major and costly problem.

On this page, I post a weekly report for you, so you will know which streets to avoid during the construction period.

Work Plan for the period July 26 to July 30, 2010
Street From To Ward Type of Work
Wooten Way South Hwy. No. 7  Delmark Boulevard 5 Asphalt Rehabilitation
Bakerdale Dr Entirety 4 Asphalt Rehabilitation
Jolyn Crt Entirety 4 Asphalt Rehabilitation
Walkerton Drive Southdale Drive Southdale Drive 4 Concrete Rehabilitation
Lake Vista Entirety 4 Concrete Rehabilitation
Raymerville Drive Woolen Mill Road McCowan Road 5 Asphalt Rehabilitation
Larkin Ave Entirety 5 Asphalt Rehabilitation
Tavistock Crt Entirety 4 Asphalt Rehabilitation
Coulson Crt Entirety 4 Concrete Rehabilitation
Lake Vista Entirety 4 Concrete Rehabilitation
Valleycrest Entirety 4 Concrete Rehabilitation
Anticipated Work Plan for the following week
Street From To Ward  
Avoca Drive Swansea Road Kennedy Road 3 Concrete Rehabilitation
Eton Street Swansea Road Kennedy Road 3 Concrete Rehabilitation
Note:
1.Weather and crew accomplishment may delay completition of the proposed work within the specified time frame
2.Advance notice will be delivered to residents/occupants several days prior to commencement of construction.
3.Street are subject to removal pending budget constraints
Rehabilitation Work Completed to Top Asphalt
Street From To Ward Type of Work
Pipher Gate Larkin Ave Tilman Cir 5 Asphalt Rehabilitation
Tilman Cir Larkin Ave Tilman Cir 5 Asphalt Rehabilitation
Follett Crt Larkin Ave North Limit 5 Asphalt Rehabilitation
Daniel Crt Entirety 5 Asphalt Rehabilitation
Enos Gate Entirety 5 Asphalt Rehabilitation
McCarty Court Heisey Dr Fincham Avenue 5 Asphalt Rehabilitation
Heisey Larkin Ave McCarty Crt 5 Asphalt Rehabilitation

 

Top of Page


Welcome

This web site provides a forum where I can bring you up to date on issues and events at the Town of Markham that affect the quality of living in our Ward.

To contact me regarding any issue please click here for the contact page.

Please visit this page to see what some residents of East Markham have to say about John.